M74 extension costs rise to £692m
The estimated final bill for the M74 extension through Glasgow and South Lanarkshire has risen by £35m.
According to the financial watchdog, Audit Scotland, the five-mile motorway project will now cost about £692m - more than double the original estimate.
Transport Scotland said 95% of costs were now fixed.
The remaining 5% would depend on final bills for land compensation, utility diversions and supervising the site during the three-year construction.
When the project was commissioned by the Labour/Liberal Democrat Scottish Executive, the cost was originally estimated at £250m.
In February, the cost was stated as £445m plus an allowance of about £12m to deal with mineworkings.
With the £200m already spent, this took the projected cost to £657m.
But the Audit Scotland report into public construction schemes across the country found that in many cases "early cost and time estimates were too optimistic".
A spokesman for Transport Scotland said the M74 extension would "still deliver a cost-benefit ratio of about five to one for every pound spent".
Work on the five-mile extension officially started in May.
It is expected to open in 2011, connecting the M74 to the M8, west of the Kingston Bridge in Glasgow.
bingo games
pregnancy forum
The estimated final bill for the M74 extension through Glasgow and South Lanarkshire has risen by £35m.
According to the financial watchdog, Audit Scotland, the five-mile motorway project will now cost about £692m - more than double the original estimate.
Transport Scotland said 95% of costs were now fixed.
The remaining 5% would depend on final bills for land compensation, utility diversions and supervising the site during the three-year construction.
When the project was commissioned by the Labour/Liberal Democrat Scottish Executive, the cost was originally estimated at £250m.
In February, the cost was stated as £445m plus an allowance of about £12m to deal with mineworkings.
With the £200m already spent, this took the projected cost to £657m.
But the Audit Scotland report into public construction schemes across the country found that in many cases "early cost and time estimates were too optimistic".
A spokesman for Transport Scotland said the M74 extension would "still deliver a cost-benefit ratio of about five to one for every pound spent".
Work on the five-mile extension officially started in May.
It is expected to open in 2011, connecting the M74 to the M8, west of the Kingston Bridge in Glasgow.
bingo games
pregnancy forum